Agenda item details
Approve Contract Change Orders and Accept the Wiget Ave Drainage Project Contract No. 2020-4269 as Complete
- Number:
- 583/2020
- Department:
- Community Development and Services Agency
- Description:
- Community Development and Services: Approve Contract Change Orders Nos. 1-6 and accept Contract No. 2020-4269 Wiget Ave Drainage Project as complete; authorize Public Works Director to execute Contract Change Orders, and sign and record Notice of Completion.
- Recommendation:
- The Public Works Department recommends that the Board of Supervisors approve Contract Change Orders Nos. 1-6 (CCO 1, CCO 2, CCO 3, CCO 4, CCO 5, and CCO 6) for the Wiget Ave Drainage Project Contract No. 2020-4269 and accept the subject project as complete; authorize the Public Works Director to sign CCO 1, CCO 2, CCO 3, CCO 4, CCO 5, and CCO 6, and sign and record a Notice of Completion for the project.
Background
R&R Pacific Construction was awarded the contract for the Wiget Ave Drainage Project (Contract No. 2020-4269) on May 26, 2020. The project consists of constructing a storm drain system, driveway culverts, asphalt overlay, and striping. Change order work was required during the construction of the project. The change order work is itemized below and totals $78,683.38. The final construction cost for the work including change orders is $459,095.48.
Discussion
Field change orders were given to the Contractor to perform necessary additional work as described below to complete the project:
Contract Change Order No. 1:
Lay asphalt over the utility trenches. $9,800.00
Contract Change Order No. 2:
Change the size of the storm drain manhole and pipe. Change the pipe material.
$4,100.00
Contract Change Order No. 3:
Place geosynthetic pavement interlayer over the failing asphalt roadway.
$7,487.86
Contract Change Order No. 4:
Install additional sewer main to relocate sewer services avoid conflicts with proposed storm drain pipe.
$37,459.98
Contract Change Order No. 5:
Install additional driveway culvert and change culvert material. Install additional shoring and trench plates due to failing roadway.
$10,160.82
Contract Change Order No. 6:
Perform digouts on failing roadway. Connect culvert to 48” storm drain pipe.
$9,674.72
Contract Change Orders Total: $78,683.38
The Contractor has completed the work. Once the Board accepts the project as complete, the Public Works Director will sign the change orders for payment, and file a Notice of Completion for the project with the Yuba County Recorder.
Committee Action:
The Land Use and Public Works Committee was bypassed as this project is included in the Public Works Budget and contract change orders are a routine part of construction.
Fiscal Impact:
General Fund: $0.00
Other Funds:
YWA for drainage components $325,000
LCWD $50,000
PG&E $9,800
Road Fund $74,295.48
The bid amount for project construction was $386,586.00. The total project costs are $459,095.48. Yuba Water Agency is funding $325,000. Linda County Water District (LCWD) is reimbursing the County approximately $50,000 for work included in the contract on their behalf. PG&E is reimbursing the County $9,800 for CCO 2 work. The remainder will come from the Road Fund.
Attachments
Discussed at meetings:
Minutes: No.18
Community Development and Services: Approve Contract Change Orders Nos. 1-6 and accept Contract No. 2020-4269 Wiget Ave Drainage Project as complete; authorize Public Works Director to execute Contract Change Orders, and sign and record Notice of Completion.
Community Development and Services: Approve Contract Change Orders Nos. 1-6 and accept Contract No. 2020-4269 Wiget Ave Drainage Project as complete; authorize Public Works Director to execute Contract Change Orders, and sign and record Notice of Completion.